Tracker subscription
A project-level dataset in Excel with the model exposed, a data dictionary and a dated change log, plus a short note on what moved.
SEQH Capital Research
Every dataset, tracker and model we publish is built from primary records: regulatory dockets, company filings, government awards and project disclosures. None of it is licensed from a data vendor, and you won't find it on a terminal.
Independent research on nuclear, uranium, power and photonics. No ratings, price targets or recommendations.
ScrollOur data
Trackers sold by data vendors count announcements. We separate what is announced from what is financed, licensed and building, and we keep the record current as it changes.
Dockets, filings, loan and grant awards, and commission records. Trade press finds the event; the record confirms it.
Project capital apart from parent and state funding. Signed offtake apart from memoranda.
Confirmed, Reported or blank on every field, with a dated log of each change.
Announced dates run against how long early reactors have actually taken to build.
SMR/MMR Pipeline Tracker, re-verified 9 Nov 2026. Hover or tap a row.
announced grid-scale capacity in the November census
of it backed by committed project-level capital
with no stated operation date
connected by end-2032, SEQH central case vs announcedSEQH EST
By project stage. 25 grid-scale projects, 9 Nov 2026.
By financing tier. Parent-company cash is never counted as project capital.
Source: SEQH SMR/MMR Pipeline Tracker, November 2026. Built from NRC, CNSC, DOE and company records; every input is in the workbook.
Who we serve
We work with institutional investors and family offices that want primary-record research on nuclear, the fuel cycle, power and photonics without building the dataset themselves.
Work arrives as files your team can test, not a view to take on trust.
A project-level dataset in Excel with the model exposed, a data dictionary and a dated change log, plus a short note on what moved.
A short note when a tracked project or company changes stage: a permit, a final investment decision, a financing, a slip or a cancellation.
A report and working model on a company, project or thesis you define, or record checks on a counterparty's licensing, funding and offtake.
Direct calls with the analyst who built the work, to go through the assumptions or test a question.
What a delivery looks like
Excel with live formulas, a sourced report, and monthly updates against the same definitions, so the series stays comparable over time.
Discuss an engagementScope and pricing on request.
| ID | Project | MWe | Stage | Tier | Announced | SEQH central | Grade |
|---|---|---|---|---|---|---|---|
| CA-01 | Darlington Unit 1 | 300 | CON | A | by end-2030 | H2 2032 | Confirmed |
| US-02 | Kemmerer Unit 1 | 345 | CON | B | by end-2030 | H2 2032 | Confirmed |
| US-05 | Hermes 2 | 50 | CON | B | by end-2030 | H2 2032 | Confirmed |
| US-01 | Clinch River Unit 1 | 300 | LIC | B | by end-2032 | H2 2034 | Confirmed |
| US-08 | Pioneer 1 & 2 | 600 | REV | B | by end-2032 | late 2034 | Confirmed |
| US-03 | Long Mott | 320 | REV | B | blank | late 2034 | Confirmed |
Change log, 29 Sep 2026: Clinch River Unit 1 moved from application review to licensed after the NRC issued its construction permit following a 14-month review. Financing tier unchanged at B.
Excerpt from the November tracker, shown as delivered. Rows are real records.
Recent research
Both come with the workbook behind them. Samples go out by email on request.
A re-verified census of 41 small and micro reactor records. It separates committed project capital from parent and government funding, grades offtake by how binding it is, and tests every announced date against the delivery record of first-of-a-kind reactors.
Pursuit's reported results set against public visitation data from Parks Canada, the US National Park Service, Statistics Canada and Keflavík airport, covering price and volume, hotel occupancy, currency exposure and what the 2030 targets require.
Coverage
Tickers are names we have published on. Coverage is not a view on any security.
Licensing dockets, DOE cost share and loans, construction progress, offtake contracts, and announced timelines set against what early reactors have taken.
Mine development and permitting, conversion and enrichment capacity, HALEU supply, isotopes, and the contracting between them.
Data-centre load, hedged and contracted generation, state rules on large loads, interconnection, and behind-the-meter supply.
Indium phosphide lasers, optical transceivers and their inputs, including supply concentration in erbium and other materials.
Standards
The same rules apply to a newsletter line and to a project dataset. Where the record is thin, we say so.
SEQH Capital Research publishes research only. We do not issue ratings, price targets or buy, sell or hold recommendations, in investor work or in issuer-sponsored coverage. Corrections run in the next edition.
For companies
Paid coverage, clearly labelled as paid, written to the same standard as our investor work.
Ask for a scopeThe business, the assets, the regulatory path and the numbers, sourced and dated. One-time fee.
A monthly fee. We are on call and publish a note whenever you put out a release.
Published through the SEQH newsletter at seqhresearch.com and SEQH's X account.
Companies may check our work for factual accuracy. Conclusions are SEQH's, and every sponsored report states that it is paid for and on what basis.